Introduction (Sir Ed): Discussion of Agenda Safety Moment (Sir Ben) *Review of the previous meeting's MOM *Draft to be submitted to sir Marlon on Friday (January 23, 2026) (Sir Ed) *Prioritize and monitor housekeeping (Plantwide) (SHE Team) *Follow up with Contractors' Temporary Facilities *(August 26) Observations raised by managers during TMM Meeting (Accomplished) *(February 12) Walkdown, Man Com (Discuss Actionable Items) CONTRACTOR'S SAFETY MANAGEMENT (Sir Aeron) *Memo release (January 16) *SFI First Aider Deployment follow up *PISAS meeting (Accomplished) >> Follow up concerns during previous meeting (January 12) *Regional TBG Working Group (Sir Ed and Sir Rod) >> Changes in PTW processes *Scaffolding validity to be included in the permit >> Prioritize renewal of permit (No renewal = No extension) -PTW - Duration of validity -Standard Time (Maximum of one day validity) >> Failure to renew leads to closure of activity (PTW discussion will be reviewed next meeting.) -Special cases -Breakdown of violations -Surrendering lock key ENVI (Sir Vic) *Emergency PR extension (Normal) *Settlement of 2026 Contracts *Bins signage/labels (Not yet settled) >> w/ Tagalog translations (Deadline: January 23) *Disposal of bins from sites (Accomplished) (Sir Erik) *Induction Stickers (Accomplished) *Require visitors to provide their own PPE before entering the Mainplant Area (++ Designated baggage area) *PR Maximo (Sir Aeron, Sir Romeo, Sir Michael) >> SR by Sir Erik *IMS update (January 26) -IMS Orientation - Online & self-paced (30%) -Aiming for 100% compliance ERM (Sir Ben) *Disposal of non-valuable barricades (Ongoing) *Relocation of barricades and bollards (Log monitoring, chain + lock) *EVAC Plan update (Outdated) >> TOR handled by TSM SHE Team *Assign acceptors from contractors (No dual roles (Authorized Personnel/Acceptor) single-work contract basis *Increase contractor awareness (Initiative by Ma'am Chella, assisted by SHE Team) *PCCP Outage update by January 23 *TBG-wide certification review as one business unit (Review scope) *Consideration of Saturday work extension & Weekdays overtime work (Sir Ed) *Rewrite new contract including single-work contract as reference (No AWS = No work) *Assessment for AWS (memo) >> hand over to Sir Aeron for registry *Initiative for more campaign and propaganda (SHE Team) (Sir Mic) *HIRAC & ICA Certifications review with incidents FINDINGS/CONCERNS: (Sir Aeron) *Signatories (Penalty, consequences shouldered by acceptors/supervisors/safety officers) -Inboxed emails (Warning) = non-compliance >> Warning notice will be recorded (Registry) -Well-performing acceptors will be rewarded (Sir Romeo) *Own padlock should be provided under OTW process >> Instigate warning notice *Padlocks: 15 (MH), 30 (OPS) Padlock controller -Padlocks with individual and single keys per lock only >> Contractors will be held responsible for further mishaps (Sir Mic) PTW Audit *Isolation points awareness *Safety documentations should be settled first before proceeding to their areas of work (Isolation witnessed by: acceptor/operator/acceptor) *PTW awareness concerns every Wednesday *Monthly PTW meeting with MNT *Meeting with ETSV (February) *No Weekly PTW meeting (Monthly PTW meeting participation only) *Contractors' Monthly Meeting (January 22, Thursday) (Sir Vic) *Heavy equipment (MH) utilization for bin disposal and relocation *Weekly washdown (Sir Ben) *Expected trainings (Late payments) *Earthquake Drill (January 20) ++ Emergency Ambulance *1 drill request for outage contractors (Sir Erik) *Special Order Closing Remarks: Sir Ben Next SHE Committee Meeting (January 20, Tuesday) 1:30 to 3:00 PM